rilpoint_mw113

Test - Parallel

1. A Parallel Test requires the processing functionality to be tested at the alternate site.

Related Terms: DR Plan Test Cycle.

Note: Parallel test will actually allow the organization to find out if the DR plan actually works. An example is the confirmation that when a procedure requires the application to be started, the personnel responsible will start the application at the alternate site. It requires the personnel to actually perform the steps in their response procedures.


BCMBoK Competency Level (CL)
BCMBoK 6: Testing and Exercising CL 3B: Advanced (BC)




BCMBoK Competency Level (CL)
BCMBoK 6: Testing and Exercising CL 2D: Intermediate (DR)

(Source: Business Continuity Management Institute - BCM Institute)